Starting tomorrow, Wednesday, June 22, Camden County will begin a series of roadway improvements along Union Ave.
Running along Union from Park to Maple avenues, the scope of the project includes asphalt roadway milling and paving; installation of new stormwater inlets and piping to improve drainage; improvements to handicap ramps; traffic striping, signs, and raised pavement markers; and installation of concrete curbing, as well as the replacement of in-kind driveway aprons, as needed.
This roadwork will utilize lane shifts, so no closures are anticipated.
The estimated duration of the roadwork improvements is 150 calendar days from June 22, weather permitting.
Project updates and additional information can be found at CamdenCounty.com/RoadUpdates. For questions, contact the Camden County Public Works 24-hour hotline at (856) 566-2980.